Nashville International Airport Hangar

Customer

Messer Construction

Owner

Nashville International Airport

Industry

Project Size

92,000 Square Feet

Project Location

Nashville, TN

Lithko Location

The Nashville International Airport is undergoing a $1.2 billion dollar renovation that will be able to support the anticipated 20 million passengers by the year 2035. Lithko has been a big part of the changes so far completing 3 other hangars along the same road.

For this project Messer sought us out due to our experience with similar projects, to complete the heavily reinforced structural slab on grade. The slab included grade beams that were capped over in order to set a 77 foot tall steel frame building. The hangar will be used by several airlines for plane repair.

The schedule changed many times throughout the process and we were eventually given 7 weeks to complete the project. We were able to pour 1,000 cubic yards of foundations in 6 days. With manpower of 35-40 people, we poured 15,000 square feet of slab every 3rd day. We also self-performed the 430 tons of rebar installation.  Messer did a good job stoning the pad prior to the concrete to ensure that weather would not be a problem.

Projects

Filter by:

Edited 600 S Tryon (2)

600 South Tryon

Description: Our Charlotte team used their expertise to successfully execute 25 floors of the cast in place structure, stairs and...

The Pearl Education & Research Buildings

Description: The Pearl buildings demanded, continuous logistical adaption due to the adjacent site infrastructure upgrades, including main powerlines. Starting with...
Factor 52 HGC PG (2)

Kenilworth Parking Structure

Scope of work: Foundations, walls, columns, slab on grade, framed deck, cast in place...

Locations

With locations all across the country, there are opportunities for you to join our team in a city near you.