Bridge Park Building Z

Customer

Brackett Builders, Inc.

Owner

Crawford-Hoying

Industry

Project Size

58,000 square feet

Project Location

Dublin, OH

Lithko Location

Bridge Park, a new up and coming neighborhood in Dublin, OH will offer residential and retail space connected by walking paths and a bridge over the Scioto River. The development will be built in several phases starting in September 2015 with an expected overall completion date of fall 2018. Brackett Builders selected Lithko to perform the concrete construction on Building Z, A-Block Parking Garage & Convention Center, and the AC Marriott Hotel.

Building Z consists of a 4 story post tension garage, 1 story of retail space and 7 stories of residential space. Each level of the parking structure will offer private garages which will connect directly with the residences.

The logistics of the site has proven to be very difficult, with a high traffic street on one side of the project and the Scioto River on the other, allowing for no parking or lay down space. There is only one way in and out of the site, a single lane switch back drive. Detailed coordination of the material deliveries and traffic in and out of the sight has required precise and timely planning. Additionally, due to the limestone rock face on the west side of the building, Lithko had to drill 70 feet on the south and fill 15 feet on the north to create the retaining wall.

In a joint effort, with Brackett Builders we have been able to keep to the project schedule, by determining the sequence of framing and assisting with cost containment by utilizing our Project Execution Process.

http://www.bridge-park.com/

 

Projects

Filter by:

Edited 600 S Tryon (2)

600 South Tryon

Description: Our Charlotte team used their expertise to successfully execute 25 floors of the cast in place structure, stairs and...

The Pearl Education & Research Buildings

Description: The Pearl buildings demanded, continuous logistical adaption due to the adjacent site infrastructure upgrades, including main powerlines. Starting with...
Factor 52 HGC PG (2)

Kenilworth Parking Structure

Scope of work: Foundations, walls, columns, slab on grade, framed deck, cast in place...