Executive Park Logistics Center Buildings 1 and 2

Customer

Miller Stauch Construction

Owner

MDC, Inc.

Project Size

378,000 square feet

Project Location

Kansas City, MO

Lithko Location

After the completion of the successful project, Schier Products with Miller Stauch, Lithko’s Kansas City BURG was awarded two buildings for the Executive Park Logistics Center. Our scope on the two buildings is comprised of foundations, tilt up panels, and dock paving.

Staying in front of the planning is essential on this job due to lumber/materials shortages and the fast-paced project schedule. We are constructing both buildings at different times, but it is critical we erect the panels successively to beat the winter weather.

Originally, the slabs were unreinforced, but are now altered to reinforced, adding to the complexity of the fast-paced schedule. The subgrade is unable to support the load of concrete trucks, so we increased the number of pours to utilize pumps instead.

We are currently placing the slabs and should wrap-up with the panels by mid-December. The success of this project could potentially lead to new buildings on the same campus.

Projects

Filter by:

Lilly Concord

Scope of Work: Basement: 90,000 square feet, 22 feet tall cast in place walls 42,000 cubic yards of concrete Concrete...
Eastgate1 2 100821 249

Prologis Buildings 1, 2, 3

Scope of Work: Foundations, slab on grade, tilt-up panels, paving Description: The project encountered unique challenges such as integrating steel...
Project Night

Project Night

Scope of Work: Foundations, tilt-up panels, Ductilcrete Heidebed System, miscellaneous site work Description: In 2021, we constructed a new storage...

Locations

With locations all across the country, there are opportunities for you to join our team in a city near you.