IDI Lakeland

Customer

Bunnell Hill Construction

Owner

IDI Logistics

Project Size

325,000 square feet

Project Location

Burlington, KY

Lithko Location

IDI Logistics is expanding its presence in Northern Kentucky. Lithko’s Cincinnati BURG is the concrete contractor on the 325,000 square foot tilt up spec building. The slab is designed and installed with the Ductilcrete Heidebed extended joint floor system.

Schedule was the greatest challenge on this project. After the first slab pour, our team faced inclement weather for 3 weeks. Despite completing the last 6 placements in the 2 weeks following the weather delay, there were 134 tilt panels that still needed built and placed.  It was crucial we adhered to the original panel erection schedule to ensure crane availability and steel delivery could be maintained. for. Our team successfully accelerated our plan and completed 6 tilt placements in 2.5 weeks, regaining time lost on our slabs and ensuring we maintained the steel erection schedule.

The team is currently pouring the topping slabs and should wrap up the project mid-February.

Projects

Filter by:

U.S. Motorworks (16)

U.S. Motorworks

This manufacturing facility project features a complex tilt-up concrete structure built into a steep hillside, including a cast-in-place retaining wall...
Pecan Deluxe 5 (1)

Pecan Deluxe 5

This manufacturing facility project featured a large industrial cooler with high-tolerance sloped concrete floors designed to manage water from candy...
Freshpet Manufacturing Expansion (2)

Freshpet Manufacturing Expansion

The Freshpet manufacturing facility required specialized industrial concrete construction, including high-tolerance sloped slabs, precision-formed curved concrete curbs, and freezer slab...

Locations

With locations all across the country, there are opportunities for you to join our team in a city near you.