The University of Oklahoma Cancer Institute

Customer

Manhattan Construction Group

Owner

University of Oklahoma

Industry

Project Size

30,000 cubic yards

Project Location

Oklahoma City, OK

Lithko Location

The  University of Oklahoma Cancer Institute  is one of only three sites in the nation that offers proton therapy with the MEVION S250 system. When Manhattan Construction Group was hired to build the seven-story hospital, they entrusted Lithko with all the concrete work, including two vaults for the proton-generating accelerators and four additional vaults for conventional radiation therapy accelerators.

Proton vaults, extending 12 feet below the basement, were the last part designed and the last bid package awarded. To avoid a three-year wait, we worked with the general contractor and design team to redesign the foundations and vault connections to allow construction of the hospital first.

The proton vaults enable the proton machine to be in the room with the patient. The machine is supported by two 8,000-pound steel embeds and rotates 180 degrees around the patient, who is on a cantilevered cast-in-place deck. The vaults were constructed within a tolerance of 1/8 inch from isocenter and consisted of eight 14-feet-wide, 34-feet-tall concrete walls. Special precautions were required during curing to ensure we adhered to the project’s thermal modeling plan. The aggregate in the concrete was 3-plus inches, requiring a combination of concrete conveyor and crane/bucket methods to place the concrete. The largest wall pour was over 1,200 cubic yards.

We were told by the team that later installed the proton machine that of the seven facilities being constructed around the country at the time, ours had the best quality, was the cleanest and had the tightest tolerance.

Projects

Filter by:

Nationwide Childrens Hospital Garage - Columbus Ohio

Nationwide Children’s Hospital Silver Garage

Scope of work: 9-level parking structure 2 below grade 7 above grade 2 elevator/stair sets Cast-in-place concrete work 26’ tall...

Village Shalom

Village Shalom’s $47 million expansion includes an assisted living community and a free-standing memory care facility. Lithko is installing the...

The Children’s Center Bed Tower and Parking Garage

The $22 million expansion for The Children’s Center will increase the number of patient beds and it will bring higher...