TransPak Industrial

Customer

Arco Murray

Owner

TransPak Industrial

Project Size

715,000 square feet

Lithko Location

This industrial warehouse construction project included two large-scale facilities for a crating and packaging company, featuring continuous and spread footings, slab-on-grade construction, tilt-up concrete panels, and dock leveler pits.

The project incorporated 156 tilt-wall panels ranging from 20 to 49 feet tall, along with extensive site concrete work including paving, sidewalks, and drainage channels. In total, the team placed more than 21,000 cubic yards of concrete and installed 590 tons of reinforcing steel, showcasing expertise in tilt-up warehouse and industrial concrete construction.

Projects

Filter by:

U.S. Motorworks (16)

U.S. Motorworks

This manufacturing facility project features a complex tilt-up concrete structure built into a steep hillside, including a cast-in-place retaining wall...
Pecan Deluxe 5 (1)

Pecan Deluxe 5

This manufacturing facility project featured a large industrial cooler with high-tolerance sloped concrete floors designed to manage water from candy...
Freshpet Manufacturing Expansion (2)

Freshpet Manufacturing Expansion

The Freshpet manufacturing facility required specialized industrial concrete construction, including high-tolerance sloped slabs, precision-formed curved concrete curbs, and freezer slab...

Locations

With locations all across the country, there are opportunities for you to join our team in a city near you.