NPD-CSX

Distribution Centers

A large parcel carrier is moving forward with the construction of a new distribution center in NorthPoint Development’s Logistics Park. Lithko’s Columbus BURG’s scope includes foundations, slab on grade, site paving, and tilt-up panels. There are 174 panels with an average height of 44’. 

Schedule is the largest challenge on the project to date. We encountered a 4 week delay due to site conditions, which accelerated the concrete scope’s schedule to maintain the building steel milestone date.  Our field operations did a tremendous job with their speed of execution. It took only 8 weeks from the start of foundations to stand the last panel. Our team placed 14,120 cubic yards of concrete in two months to achieve the milestone date.