Nexton MOB
Healthcare
The Nexton MOB is part of the first phase of a new medical campus in Summerville, South Carolina. This development will provide primary, specialty and urgent care services to the Nexton community, bringing more than 250 jobs to the area. Our Charleston team installed the foundations, elevator and stair cores, slab on-grade and the slab on metal deck for this building.
The specific crane lifted formwork system was identified during our upfront planning meeting to assemble the cores. Our daily plan included a crane schedule with fifteen minute increments that allowed the sequence to be optimized for each concrete lift, resulting in a 3-day cycle on the cores reducing the overall schedule and cost for the project.
Details
Customer Equity Construction Solutions
Owner Palmetto Primary Care Physicians
Size (finished slab) 100,000 square feet
Location Summerville, SC
Other Projects in Healthcare