NPD-CSX

Distribution Centers

A large parcel carrier is moving forward with the construction of a new distribution center in NorthPoint Development’s Logistics Park. Lithko’s Columbus BURG’s scope includes foundations, slab on grade, site paving, and tilt-up panels. There are 174 panels with an average height of 44’.

Schedule is the largest challenge on the project to date. We encountered a 4 week delay due to site conditions, which accelerated the concrete scope’s schedule to maintain the building steel milestone date.  Our field operations did a tremendous job with their speed of execution. It took only 8 weeks from the start of foundations to stand the last panel. Our team placed 14,120 cubic yards of concrete in two months to achieve the milestone date.

Details

Customer Meridian Design Build, LLC
Owner NorthPoint Development
Size (finished slab) 400,000 square feet
Location North Baltimore, OH