Volvo Project Amazon
This structure is an addition to an existing car plant manufacturing facility. Lithko’s scope consists of a 200,000 square-foot mineral dry shake slab on grade processing and logistics area. In addition to the added manufacturing space, our team is responsible for 193,000 square feet of site paving around the plant.
The project has two phases:
- 80% of the project was completed in 2021 and took about 6 months.
- The second phase of the project began in April 2022 and is estimated to take 3 months to complete.
Unique challenges:
The mineral dry shake floor was the biggest challenge on this project due to the precise nature of application parameters. The building had to be 100% enclosed and dried-in prior to placement of slabs, so coordination with the GC and other trades was imperative.
Like many companies and projects, our team encountered material supply shortages for this project in 2021. We worked closely with the GC to navigate how these supply chain challenges would impact the overall schedule and turnover of slab areas.